What permits does your project need?

Pick your project and see the permits required, the departments involved, the forms to file, and a realistic timeline. Free, no signup.

Permit and plan check required

ADU — detached new construction

Standalone ADU built from scratch in the yard. Most flexible, longest timeline.

Permit
Building Permit
Typical timeline
90–180
business days

Trades typically involved

  • Electrical — new circuits, outlets, fixtures
  • Plumbing — fixtures, water lines, drains
  • Mechanical / HVAC — heating, cooling, vents

Departments involved

LADBSLos Angeles Department of Building and Safety

Issues all construction permits, runs plan check, and performs inspections through final.

  • · Building Permit
  • · Plumbing Permit
  • · Electrical Permit
  • · Mechanical / HVAC Permit
City PlanningLos Angeles Department of City Planning

Verifies zoning compliance, setbacks, height limits, and lot coverage under state ADU law.

  • · Zoning Clearance
BOSBureau of Sanitation

Reviews sewer capacity and collects sewer connection fee for the new dwelling.

  • · Sewer Capacity Availability Request
  • · Sewerage Facilities Charge (SFC)
BOEBureau of Engineering

Issues encroachment permits if new driveway, curb cut, or sidewalk work touches the right-of-way.

  • · Driveway / Curb Cut Permit (B-Permit if applicable)
LAHDLos Angeles Housing Department

Required ADU covenant recording and rental registration.

  • · ADU Covenant Recording
  • · Rental Registration (if rented)
LAFDLos Angeles Fire Department

Reviews fire access, sprinklers (if main house has them), and hillside defensible space.

  • · Fire Department Plan Review (hillside / sprinkler triggers)

Forms you’ll file

  • · Building Permit Application
  • · Plumbing Permit Application
  • · Electrical Permit Application
  • · Mechanical / HVAC Permit Application

What to expect

  • · State law requires ministerial permit processing — no neighbor input, no discretionary review.
  • · Building department has 60 days to approve a complete ADU application.
  • · ADU permit fees protected by state code.
  • · Setbacks reduced to 4 feet by state law for new ADUs.
  • · No replacement parking required even if displacing existing parking.

Common pitfalls

  • · Hillside lots may require grading review and soils reports.
  • · Sewer connection capacity sometimes requires upgrade.
  • · Fire sprinklers required if main house has them.
  • · Existing 100A electrical service may not support an additional dwelling.
  • · Title 24 energy compliance can require unexpected envelope upgrades.
  • · Drainage and stormwater management often missed during design.
Want the fee estimate?

Open the calculator pre-filled for this project.

Estimate the fee
Already did this work without a permit?
You can usually still legalize it with a retroactive permit. See how to fix unpermitted work.

Informational only. Requirements are set by LADBS and can vary with your exact scope. Confirm before starting work.