What permits does your project need?
Pick your project and see the permits required, the departments involved, the forms to file, and a realistic timeline. Free, no signup.
Permit and plan check required
Deck construction
New or replacement wood/composite deck attached to house.
Permit
Building Permit
Typical timeline
14–45
business days
Departments involved
LADBSLos Angeles Department of Building and Safety
Reviews ledger attachment, footing depth, railing height, and stair geometry. Inspects each stage.
- · Building Permit (Deck)
City PlanningLos Angeles Department of City Planning
Verifies setbacks (often more restrictive than the main house) and lot coverage.
- · Zoning Clearance
Forms you’ll file
- · Building Permit Application
What to expect
- · Decks over 30" above grade require permit and railings.
- · Decks over 200 sq ft typically require permit.
- · Ledger attachment to house is the primary structural concern.
- · Footings must extend below frost line where applicable.
Common pitfalls
- · Improper ledger attachment is the #1 cause of deck failures.
- · Setback requirements often more restrictive than for the main house.
- · Stairs to grade require landings of specific dimensions.
Want the fee estimate?
Open the calculator pre-filled for this project.
Already did this work without a permit?
You can usually still legalize it with a retroactive permit. See how to fix unpermitted work.Informational only. Requirements are set by LADBS and can vary with your exact scope. Confirm before starting work.