What permits does your project need?
Pick your project and see the permits required, the departments involved, the forms to file, and a realistic timeline. Free, no signup.
Express permit
HVAC / furnace replacement
Replacing furnace, AC, or heat pump with same size and rating. No vent relocation.
Permit
Express Mechanical Permit
Typical timeline
1–3
business days
Trades typically involved
- Mechanical / HVAC — heating, cooling, vents
Departments involved
LADBSLos Angeles Department of Building and Safety
Issues the express mechanical permit at the counter; rough-in and final inspections by mechanical inspector.
- · Express Mechanical Permit
Forms you’ll file
- · Mechanical / HVAC Permit Application (Express pathway)
What to expect
- · Express Permit pathway — no drawings, no plan check.
- · Permit issued within 1–3 business days.
- · Inspection scheduled separately after install.
- · Same-size, same-Btu, no vent relocation required for Express pathway.
Common pitfalls
- · Changing size or BTU rating shifts to standard permit pathway.
- · Vent relocation triggers plan check.
- · Smoke/CO detectors must be installed throughout home.
- · Refrigerant line replacement may trigger separate refrigerant handling certification.
Want the fee estimate?
Open the calculator pre-filled for this project.
Already did this work without a permit?
You can usually still legalize it with a retroactive permit. See how to fix unpermitted work.Informational only. Requirements are set by LADBS and can vary with your exact scope. Confirm before starting work.