What permits does your project need?

Pick your project and see the permits required, the departments involved, the forms to file, and a realistic timeline. Free, no signup.

Express permit

HVAC / furnace replacement

Replacing furnace, AC, or heat pump with same size and rating. No vent relocation.

Permit
Express Mechanical Permit
Typical timeline
1–3
business days

Trades typically involved

  • Mechanical / HVAC — heating, cooling, vents

Departments involved

LADBSLos Angeles Department of Building and Safety

Issues the express mechanical permit at the counter; rough-in and final inspections by mechanical inspector.

  • · Express Mechanical Permit

Forms you’ll file

  • · Mechanical / HVAC Permit Application (Express pathway)

What to expect

  • · Express Permit pathway — no drawings, no plan check.
  • · Permit issued within 1–3 business days.
  • · Inspection scheduled separately after install.
  • · Same-size, same-Btu, no vent relocation required for Express pathway.

Common pitfalls

  • · Changing size or BTU rating shifts to standard permit pathway.
  • · Vent relocation triggers plan check.
  • · Smoke/CO detectors must be installed throughout home.
  • · Refrigerant line replacement may trigger separate refrigerant handling certification.
Want the fee estimate?

Open the calculator pre-filled for this project.

Estimate the fee
Already did this work without a permit?
You can usually still legalize it with a retroactive permit. See how to fix unpermitted work.

Informational only. Requirements are set by LADBS and can vary with your exact scope. Confirm before starting work.