What permits does your project need?

Pick your project and see the permits required, the departments involved, the forms to file, and a realistic timeline. Free, no signup.

Express permit

Water heater (tank) replacement

Replacing existing tank water heater with same gallonage and Btu rating.

Permit
Express Plumbing Permit
Typical timeline
1–3
business days

Trades typically involved

  • Plumbing — fixtures, water lines, drains

Departments involved

LADBSLos Angeles Department of Building and Safety

Issues the express plumbing permit at the counter; final inspection by plumbing inspector.

  • · Express Plumbing Permit

Forms you’ll file

  • · Plumbing Permit Application (Express pathway)

What to expect

  • · Express Permit. Per-fixture fee from plumbing schedule.
  • · Seismic gas shut-off valve required if not already installed.
  • · Earthquake straps required (two straps, upper and lower third of tank).
  • · Drain pan required when located in habitable space or attic.

Common pitfalls

  • · Vent relocation triggers fuller permit pathway.
  • · Going from gas to electric requires additional electrical permit.
  • · Garage installation requires elevation 18 inches off floor or sealed-combustion unit.
  • · Thermal expansion tank required when supply has a backflow preventer or pressure regulator.
Want the fee estimate?

Open the calculator pre-filled for this project.

Estimate the fee
Already did this work without a permit?
You can usually still legalize it with a retroactive permit. See how to fix unpermitted work.

Informational only. Requirements are set by LADBS and can vary with your exact scope. Confirm before starting work.